Owner: 

Hyannis Fire District

Architect: 

Kaestle Boos Associates Inc

Location: 

Hyannis, MA

Size: 

32,400 sf

This project is a multi-phased construction of a new Fire Headquarters Facility consisting of approximately 32,400 sq ft. Phase One will be the construction of approximately half of the apparatus bays and the entire two story administrative and fire fighters living quarters.

Once Phase One is completed and occupied, Phase Two will commence. Phase Two will consist of hazardous materials abatement and demolition of the existing fire headquarters building.

Upon completion of Phase Two, Phase Three will commence with the construction of the remaining apparatus bays and associated site work.

The exterior will be masonry, with light gage metal frame back-up. The roof structure will be a combination of truss construction at sloping areas, and steel / metal deck at low-slope roof areas. Interior partitions will be a combination of masonry and light gage metal framing. Interior finishes will include CMU walls, painted gypsum walls and ceilings, acoustic ceiling tile, ceramic tile, resilient flooring, epoxy flooring and carpet. Building systems will include equipment and systems to provide complete electrical, plumbing fire suppression / sprinklers, and HVAC services.

Other elements of work include site clearing, concrete, site infrastructure & utilities, communications tower and provisions of all new building utility services (power, water, sanitary, etc).